LEGEND. Jurmala

Report of completed construction works on 31.10.2014

Villa Dietrich
Ongoing hall and staircase finishing work. Villa Tiffany Completed facade restoration, ongoing interior finishing work according to the interior design.
 
Villa Hemingway Ongoing interior finishing work according to the interior design.
 
Villa Churchill Completed installation of the utilities, heat supply connected in the building; Ongoing installation of the assembly of the decorative fixtures on the facade of the building. Hall and staircase finishing work commenced.
 
Villa Hepburn Completed facade glazing work, installation of the decorative fixtures on the facade of the building, and installation of the apartment partitions.Ongoing thermal insulation and terrace waterproofing work. Ongoing hall and staircase finishing work in accordance with the interior design. Installation of the interior partitions and the ceiling, installation of the utilities and the pool equipment ongoing in the SPA area.